The Congressional Research Service has issued an updated report on Coast Guard Cutter procurement by Specialist in Naval Affair, Ronald O’Rourke. It is available in pdf format here or you can read it on the US Naval Institute site here.
Quoting from the Report,
Summary
The Coast Guard’s acquisition program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard’s proposed FY2018 budget requests a total of $794 million in acquisition funding for the NSC, OPC, and FRC programs.
NSCs are the Coast Guard’s largest and most capable general-purpose cutters. They have an estimated average procurement cost of about $695 million per ship. The first six are now in service (the sixth was commissioned into service on April 1, 2017). The seventh, eighth, and ninth are under construction; the seventh and eighth are scheduled for delivery in 2018 and 2019, respectively. As part of its action on the Coast Guard’s FY2017 budget, Congress provided $95 million for procurement of long lead time materials (LLTM) for a 10th NSC. The Coast Guard’s proposed FY2018 budget requests $54 million in acquisition funding for the NSC program; this request does not include additional funding for a 10th NSC.
OPCs are to be smaller, less expensive, and in some respects less capable than NSCs. They have an estimated average procurement cost of about $421 million per ship. The first OPC is to be funded in FY2018 and delivered in 2021. On September 15, 2016, the Coast Guard announced that it was awarding a contract with options for building up to nine ships in the class to Eastern Shipbuilding Group of Panama City, FL. The Coast Guard’s proposed FY2018 budget requests $500 million in acquisition funding for the OCP program for the construction of the first OPC, procurement of LLTM for the second OPC, and certain other program costs.
FRCs are considerably smaller and less expensive than OPCs. They have an estimated average procurement cost of about $65 million per boat. A total of 44 have been funded through FY2017. The 24 th was commissioned into service on October 31, 2017. The Coast Guard’s proposed FY2018 budget requests $240 million in acquisition funding for the procurement of four more FRCs.The NSC, OPC, and FRC programs pose several issues for Congress, including the following:
-
whether to fully or partially fund the acquisition of a 10th NSC in FY2018;
-
whether to fund the acquisition of four FRCs in FY2018, as requested, or some other number, such as six, which is the maximum number that has been acquired in some prior fiscal years;
-
whether to use annual or multiyear contracting for procuring FRCs;
-
whether to use annual or multiyear contracting for procuring OPCs;
-
the procurement rate for the OPC program;
-
planned procurement quantities for NSCs, OPCS, and FRCs;
-
the cost, design, and acquisition strategy for the OPC; and
-
initial testing of the NSC.
Congress’s decisions on these programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base.